General . by quaero 8/3/2014 written by quaero 8/3/2014 A can complete a work in 12 days and B can complete the same work in 24 days. In how many days A and B together complete the work? work 1 comment 0 Email Related posts Atheists (and agnostics, misotheists, deists) what keeps you... 3/18/2026 11 Weeks 3/17/2026 Give and Take 3/16/2026 Single And Alone vs Mediocre Relationship 3/16/2026 It’s so easy 3/16/2026 Baby Steps 3/15/2026 Stagnant- Not Progressing in Life 3/15/2026 The Psychology of Cruelty 3/15/2026 Mediocrity vs Greatness 3/14/2026 Sitting Here Listening To This Song 3/14/2026 1 comment tbd 8/3/2014 - 6:49 am Really? No one? 1/12 + 1/24 = 1/t 2/24 + 1/24 = 1/t 3/24 = 1/t 24/3 = t 8 = t Theoretically, 8 days, but if they are talking and shooting the s—, it will probably be 10, maybe 15 if they are really having a good time. Log in to Reply Leave a Comment Cancel ReplyYou must be logged in to post a comment.Subscribe to comments: Don't subscribe All new comments Replies to my comments Notify me of followup comments via e-mail. You can also subscribe without commenting.
1 comment
Really? No one?
1/12 + 1/24 = 1/t
2/24 + 1/24 = 1/t
3/24 = 1/t
24/3 = t
8 = t
Theoretically, 8 days, but if they are talking and shooting the s—, it will probably be 10, maybe 15 if they are really having a good time.